Verifying DLAG Protection Switching

This topic describes the testing procedure for the DLAG protection switching that is triggered by the line failure after the fiber is removed.

Prerequisites

A DLAG protection group must be configured at station A.

The fiber connections between station A and station B must be complete.

The equipment must be running normally.

Tools, Equipment and Materials

U2000 Web LCT, SmartBits (SMB), optical fiber, flange

Test Connection Diagram

Figure 1 and Figure 2 show the DLAG protection in the normal and switching states.

Figure 1 DLAG protection (normal)

Figure 2 DLAG protection (switching)

Procedure