Verifying ODUk SNCP Switching

This section takes a ring network formed by two stations in which the tributary board and the line board are jointly used as an example to describe the test procedure of the ODUk SNCP protection switching.

Prerequisites

The ODUk SNCP protection must be configured.

The fiber connections between station A and station B must be complete.

The equipment must be running normally.

Tools, Equipment and Materials

U2000 Web LCT, signal analyzer, optical fiber, flange, optical attenuator

Set-up Diagram

The diagram of testing ODUk SNCP protection switching is shown in Figure 1.

Figure 1 Testing ODUk SNCP protection switching

: Fixed optical attenuator

1,4: Tributary Unit

2,3,5,6: Line Unit

Procedure