Uploading the Line Test Baseline

After the line test baseline is collected, the information about the test line baseline data is saved in an NE. You can upload the line test baseline data from the NE to the U2000 Web LCT, to synchronize the data between the U2000 Web LCT and the NE.

Prerequisites

The line test baseline exists in the NE.

Procedure

  1. In the NE Explorer, select an NE and choose Configuration > Submarine Cable Line Monitoring from the Function Tree.

    Figure 1 SLM 1630 V100R001

    Figure 2 SLM 1630 V100R002

  2. Enter the baseline management window in the following ways.
    • In-service mode: Select a line, click In-Service Mode and select Baseline Management. The In-Service Mode Baseline Management window is displayed.
    • Out-of-service mode: Select a line, click Out-of-Service and select Baseline Management. The Out-of-Service Mode Baseline Management window is displayed.



  3. Click Upload the Baseline and a confirm dialog is displayed, click OK to upload the baseline to the U2000 Web LCT.

Huawei Proprietary and Confidential